Here are some sample 70-348 exam questions. 70-348 dumps is really great to pass exam. It contains 70-348 practice test braindumps Q&A.

An effective 70-348 exam questions preparation and grip over the entire course contents are definitely required to pass out your Microsoft Certification exam. 70-348 dumps here are reliable, comprehensive and up to the standards having 70-348 exam questions verified by Professional Experts. Our 70-348 dumps compose of 70-348 exam questions and 70-348 practice test, come in two formats i.e. in PDF file format and Online practice test software.

By using this online test engine mode you can practice 70-348 questions answers easily for the actual Microsoft 70-348 exam. You can download and try the free 70-348 dumps demo before buying exam 70-348 PDF file from Testmayor. Our excellent 70-348 exam questions dumps is a guarantee to your success in Microsoft certification exam.

Get 70-348 exam questions dumps and pass exam in first attempt.


70-348 Exam Questions | Your organization is in the process of implementing

Question: 6

Your organization is in the process of implementing Microsoft PPM. You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects. On the Task Settings and Display page, what should you do?

A. Set the tracking method to Free form.
B. Select the check box Force project managers to use the progress reporting method specified above for all projects.
C. Clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. Set the tracking method to Percent of work complete.

Answer: A

70-348 Exam Questions | You are project manager for

Question: 5

You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project. What should you do?

A. In Microsoft Project, manage a deliverable.
B. On the project site, edit the list to include the Task ID attribute.
C. In Microsoft Project, use Sync Deliverables.
D. On the project site, create a new item in the Deliverables list.

Answer: D

70-348 Dumps | You are the administrator for…

Question: 4

DRAG DROP

You are the administrator for an organization that uses Microsoft PYou are the administrator forPM.
Users must be able to create projects by using predefined templates.
You need to create a new Enterprise Project Template and make it available for users.
In which order should you perform the actions? To answer, move all of the actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Correct Answer:

Click Here For Full File of Microsoft 70-348 Dumps Questions

70-348 Practice Test | The SharePoint Farm administrator for…

Questions: 3

The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the
URL: https://AppServer/Live.
You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.

You need to ensure that the RBS is implemented.

What should you do first?

A. Run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
B. Ask the SharePoint administrator to run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
C. From Settings, select Manage Groups.
D. From Site Settings, activate the Project Web App Connectivity feature.

Answer: B

70-348 | An organization uses Microsoft PPM to manage projects…

Question: 2

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis. You need to ensure that resources can enter their time on tasks. Which three actions should you take? Each correct answer presents part of the solution.

A. On the Task Settings and Display page, set the tracking method to Hours of work done per period
B. On the Task Settings and Display page, select Resources should report their hours worked per day
C. On the Task Settings and Display page, clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. On the Task Settings and Display page, select the check box Force project managers to use the progress reporting method specified above for all projects.
E. Instruct the project managers to select the tracking method for their project in Microsoft PPM.

Answer: A,C,D

70-348 | You use Microsoft PPM to manage an e-commerce…

Question: 1

You use Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level. You need to be able to see all programs and their associated individual projects from within Project Center. What should you do?

A. Select the Enterprise Project Type Name field as the value for grouping.
B. Select the Master Program field as the value for filtering.
C. Select the Subprojects check box.
D. Select the Project Details view.

Answer: C